Start each day on the Board โ it shows everything that needs attention across all projects.
The Permit dashboard (linked from the main dashboard) gives a one-screen view of where every project stands on its building permit and mural approval, without opening each project individually.
You don't set a project's Construction status by hand anymore โ it follows the schedule Gantt. Mark tasks as you go and the dashboards, the permit dashboard, and the project page's Construction badge all update themselves.
The Upcoming page (header link) lists every project with a construction start date and tells you when each long-lead item has to be ordered: sheet metal 10 business days before the start, materials 5, graphics 2. (Brackets are built on site, so they aren't tracked here.) Business days are Monday to Friday.
Each track has a handful of tickets โ Building Permit has Due Diligence, Contractor Reg, Submittal, and Plans; Pre-Con, Construction, and Financial each have their own list too, and every project gets all three automatically. Click any ticket row on the project page (or any ticket card on the Board) to open its drawer and work it.
Notes replace the timestamped entries you were keeping in the Email Transfer spreadsheet and Teams threads. Add a note any time something happens on a project.
Each permit track (Building, Mural, Electrical, etc.) also has its own Notes button โ separate from the Activity Log above. Use it for loose, scratchpad-style detail about that one track that doesn't belong in a status field: "I called the permit guy and he is on vacation for the next few days," "they don't have a published guide for colors, but the permit office doesn't like red," "spoke to Jason, he said to just email the plans." It never shows up on any dashboard and a client never sees it.
Mural permits follow a set order. The 4 options live as checklist lines inside the Mural track's Submittal ticket โ open that ticket and work down the list.